What percentage of prime vendor (PV) orders need to be inspected during the receipt process?

Prepare for the CDC 4A151 Volume 3 Exam. Use our interactive quiz to study with flashcards, multiple choice questions, and comprehensive explanations. Achieve your best score!

During the receipt process of prime vendor orders, it is required that 100% of these orders be inspected. This thorough inspection is critical to ensure that all items received meet the quantity, quality, and specifications outlined in the purchase orders. By inspecting every item, discrepancies such as missing items, incorrect delivery, or quality issues can be identified immediately, allowing for prompt resolution. This rigorous inspection standard is designed to maintain accountability and ensure that the organization receives the products as agreed upon, minimizing the risk of operational disruptions caused by faulty supplies.